Roof parapet at Hugh Stewart House, Nottingham, with new pale sandstone pieces fitted between dark weathered original stones. A scaffolding walkway runs alongside during Allsopp Construction's stone restoration.
Window, dormer, leadwork and stonework repairs at the Grade II listed Hugh Stewart House are nearing completion.

Our listed building repairs at Hugh Stewart House in Nottingham are progressing well. We have been on site at the University of Nottingham’s University Park campus since June. The project is due to finish before Christmas.

About Hugh Stewart House

Hugh Stewart House is one of the University’s most distinctive buildings. Nottingham banker John Wright built the Grade II listed Gothic manor house around 1800 as Lenton Hall, his country home. It later became part of the Hugh Stewart Hall complex. Today, part of the building is a hotel and venue for university visitors, conference delegates, weddings and weekend breaks.

Like any historic building, it needs careful upkeep. The main aim of this project is to keep it watertight and secure for the long term. In places, the dormer windows and the leadwork around them had started to let water in. This caused some of the timber to rot.

Listed building repairs and redecoration

The original contract was to redecorate the building’s timber and metal windows. Surveys showed that more work was needed, so the programme grew into a heritage repair, restoration and redecoration scheme. It now covers the windows, masonry, finials and turrets. Doing the repairs before redecorating gives a more durable result. It will also help protect the building for years to come.

Progress so far

Work started in June when the scaffolding went up. The stonework is now complete, and the window and roof work is nearly finished.

The team has replaced key pieces of stone and repaired others. Several turrets and decorative stones had come loose, so the stonemasons re-fixed and repaired them. A whole stone doesn’t always need replacing. Specialist stonemasons can cut out just the damaged section and fix a new piece in its place.

On the windows, the team has repaired or replaced damaged timber, metal and putty, then repainted them. The dormer windows were in a poor state, so we are replacing them along with the surrounding leadwork. We are also replacing timbers that rotted where water got in.

Who is delivering the work

We are Principal Contractor on this project. ASBC Heritage & Conservation Specialists are carrying out the specialist repairs to the timber windows, stonework and masonry. Our Site Manager, Ian Abbott, is leading the work on site. Ian has been with Allsopp for 15 years.

Hugh Stewart House is one of five live projects we are currently delivering for the University of Nottingham. It continues our long-standing relationship with the University’s estate teams.

If you have a project that you would like to discuss with us, contact: Martyn on 07971 899 646 or email info@allsoppconstruction.co.uk

Contact us

Ready to start your next project? Get in touch with us today for a free consultation.

Contact us

Ready to start your next project? Get in touch with us today for a free consultation.

Learn how we helped 100 top brands gain success