This bungalow to house conversion project is now nearing completion. Since our last update in August, we have completed all the internal building works, including full construction and plastering of the new top floor with viewing gallery and master suite.
Other works include:
- Ground Floor Upgrades: structural and internal work including re-roofing single storey lounge, raising all existing ceilings by 200mm, replastering, and the installation of underfloor heating.
- Heating System: installation of new energy-efficient systems; Air Source Heat Pump and MVHR (Mechanical Ventilation with Heat Recovery) system.
- Re-wire of the property including new lighting and sound system.
- Kitchen Reinstallation: the original kitchen units, which were carefully removed and stored, have been re-fitted into the renovated space.
The final internal work decorating and flooring is being carried out by other companies that have a direct relationship with the client. The cinema room is also currently undergoing its specialist fit-out.
Since the summer the scope of works has been extended to include several external improvements and landscaping elements.
- Entrance Steps: the old, perished entrance steps were replaced with a durable solution: steps constructed using gabion baskets and finished with porcelain. This design specifically provides superior drainage and air flow.
- Balastrade: the external appearance was modernised with the installation of a new glass balustrade, replacing the previous stone version.
- Paving and Drive: A herringbone Dutch-style patio in light grey brick was laid at the front and a new resin drive has replaced the old gravel surface.
The final job is the rendering to the ground floor of the existing bungalow. This will completely transform the exterior, tying the building’s overall look together.
We’re on track to complete and hand over the project by the end of November 2025.
If you have a project that you would like to discuss with us contact:
Martyn on 07971 899 646 or email [email protected]